GGD handed over the finished-goods warehouse to Navoiyazot

On 20 March 2023 Glory Group Development handed over a 4,300 m² finished-goods warehouse to Navoiyazot in Navoi. Construction took 12 months, starting in April 2022. The general contractor built the foundations, industrial floors, steel frame, roof and wall panels, and installed ventilation, power supply and fire safety systems. The warehouse has loading docks for road vehicles and is connected to the plant's rail spur. The work was carried out on the grounds of an operating plant: vehicle routes and working hours were agreed with the plant's security service.

Project: Navoiyazot finished-goods warehouse