| Client | Navoiyazot AJ |
|---|---|
| General contractor | Glory Group Development |
| Location | Navoi |
| Area | 4,300 m² |
| Start | April 2022 |
| Completion | March 2023 |
| Duration | 12 months |
| Status | Completed |
Glory Group Development (GGD) was the general contractor for Navoiyazot finished-goods warehouse. The client is Navoiyazot AJ. Location: Navoi. The total floor area is 4,300 m². Work started in April 2022 and was completed in March 2023; the project took 12 months. As part of the project, GGD carried out: Earthworks and foundations, Industrial concrete floors, Steel frame erection, Roofing and sandwich wall panels, Gates and loading docks, Supply and exhaust ventilation, Power supply and warehouse lighting, Fire alarm and fire suppression, Access roads and hardstanding.
To build a finished-goods warehouse of 4,300 m² on the grounds of the operating Navoiyazot plant in Navoi. The warehouse is meant for storing packaged products and loading them onto road and rail transport. The work took place on an active industrial site, so the contractor agreed vehicle routes and working hours with the plant's security service.
The 4,300 m² warehouse was completed in 12 months and handed to the client on 20 March 2023. The building has loading docks for road vehicles and is connected to the plant's rail spur. The work was carried out without stopping the operating production.
Any questions left?
Leave your contact information and we will contact you to answer all your questions!