On 2 September 2024 HUMO School Academy began the school year in a new building in the Mirzo Ulugbek district of Tashkent. Glory Group Development designed and built the 6,200 m² building. Construction ran from May 2023 to August 2024, and the building was handed to the client before classes began. It houses classrooms, laboratories, a sports hall, an assembly hall and a canteen. GGD carried out the design and construction under a single contract, so architectural and engineering decisions were agreed within one team. The engineering systems, including ventilation, heating, water supply, power supply and fire alarm, were commissioned before handover.